Work Breakdown & Three-Point (PERT) Estimates
All lessons
- Work Breakdown & Three-Point (PERT) EstimatesFree
- Schedule Dates with WORKDAY & Dependencies Pro
- Critical Path: Forward Pass, Backward Pass & Slack Pro
- Resource Loading, Cost Budget & the S-Curve Pro
- Earned Value: PV, EV, AC, Variances & Indices Pro
- Forecasting with Earned Value: EAC, ETC, VAC & TCPI Pro
- Risk Register: Scoring, Expected Monetary Value & Ranking Pro
- Status Report KPIs & RAG Status with IFS Pro
You are not signed in — the lab works, but your progress is not saved. Start free
Read first
Why not just use the most likely value?
Tasks can overrun far more than they can underrun, so the pessimistic tail is longer. PERT pulls the estimate towards that tail: for the front-end build, M is 15 days but the PERT estimate is 16. Summed over a whole project, ignoring the tail is the classic reason for late delivery.