NPV calculator
Discount a series of yearly cash flows and subtract the investment to get the net present value. The table shows the present value of each year, and the Excel formula is ready to copy.
Result
Calculating…
How to calculate it in Excel
| Cell | Put in |
|---|---|
B1 | Discount rate |
B2 | Investment today (as a negative number) |
B3:B6 | Cash flows year 1 to 4 |
=NPV(B1, B3:B6) + B2
Excel's NPV function assumes the first value arrives one period from now. That is why the investment made today is added outside the function and not put inside the range.
With your numbers (paste into any cell):
How the calculation works
NPV = −investment + CF1/(1+r)¹ + CF2/(1+r)² + … Each future cash flow is worth less today, because the same money could earn the discount rate in the meantime.
A positive NPV means the project earns more than the discount rate and adds value. A negative NPV means you would be better off with the alternative that earns the discount rate.
Questions
Why does Excel's NPV give a different answer than my calculator?
Usually because the year-0 investment was put inside the NPV range. Excel then discounts it by one year. Keep the investment outside: =NPV(rate, CF1:CFn) + CF0.
When should I use XNPV instead of NPV?
When the cash flows do not arrive at even yearly intervals. XNPV takes a list of dates and discounts each amount by the exact number of days.
Which discount rate should I use?
For company projects, usually the WACC. For personal decisions, the return you could get on a comparable investment.